Creating Partnerships for Public Services

HOME | ABOUT US | SERVICES | SECTORS | PEOPLE | NEWS | RECRUITMENT | RESOURCES | CONTACT US | FEEDBACK
OGC Guidance: ICT Contracts

Partnerships UK, the OGC and Intellect UK have published the new “Negotiating Guidance for the OGC ICT Services Model Agreement.”

The main issues that that the Guidance focuses on are supply chain rights; due diligence; authority termination for convenience and limits of liability and indemnity. This article examines each of these points in some detail and the implications of them for the procuring authority.

Supply Chain Rights - The Guidance provides a number of optional supply chain rights provisions which dependent upon the circumstances may be relevant. These include the Authority right to withhold or delay consent in certain situations; flow down provisions; the use of Direct Agreements; Authority Consent requirements for termination of sub-contracts; the Authority’s right to require a sub-contract termination in certain circumstances and the Authority’s right to use existing Authority sub-contracts that are more favourable than those negotiated by the contractor.

It should however be borne in mind that the inclusion of the provisions should be considered with reference to the project specifics in order to avoid delay due to greater negotiation and added costs in the private sector accepting all the added risks when not appropriate.

As such procuring authorities should ensure when negotiating that critical services are not put at risk by supply chain failures; the contracts only pass down those provisions that are appropriate to the sub-contractors role in delivering the services and the continued provision from a critical sub-contractor is protected even if there are problems with the contractor to maintain service delivery.

Due Diligence - The Guidance confirms that due diligence provisions are essential as they place a clear responsibility on the contractor to ensure that the site and system is understood and fit for those services. The contractor is therefore liable for any further work needed which was not identified. This position requires the Authority to support and assist the contractor in carrying out the due diligence and table sufficient time. In recognition of the fact that this is not always the case the Guidance provides the option of a price varying mechanism to address certain due diligence risks.

Authority Termination for Convenience – Authority rights to terminate for convenience are set around the principle need to protect the public purse in the event of a change in Government or policy. The Guidance recognises the importance of this provision given the pending General Election, but also the disproportionate impact that this could have on a contractor, particularly in lager more complex projects where they were seeking to recover costs over a number of years.

The Guidance highlights the need for the Authority in negotiating any such voluntary termination provisions to be mindful of the impact and sensitivity of this issue for the contractor although in reality such termination is ordinarily only a last resort. In addition the Authority may wish to consider the relative benefits of setting an initial period when the termination for convenience provisions could not be invoked, thus reducing the risk on the contractor and in turn the premium that the contractor will charge to include taking on such risk.

Limits of Liability & Indemnity – The Guidance confirms that these provisions should set out an allocation of risk and a cap on the extent of that risk for each party on a case by case basis. The Guidance clarifies that commercial organisations should only be expected to have levels of liability that are proportionate to the risks and potential financial returns of the project. The Guidance recommends that Authority’s lead negotiations on these provisions with a realistic idea of the limits of liability. If the liability is not proportionate to the risks this may reduce value for money by way of increased premiums set by the contractor to take account of the added risks. The Guidance clarifies that only liabilities that can not be limited by law should remain uncapped; all risks should be assessed on a case by case basis and the Authority should ensure that risks flow down correctly into any sub-contracts. Finally the Guidance clarifies that an indemnity in respect of IT infringements should be used in every case irrespective of circumstance.

For procuring authorities there may be the temptation to try to push as much risk as possible onto the contractor, however in reality this will only lead to long drawn out and difficult negotiations and an price that no longer reflects value for money as the contractor will add a price to take on any additional risk and particularly those risks that they are not best placed to manage.

In conclusion procuring authorities need to ensure that they fully understand the services that they are procuring and the specifics of the case, allow adequate time for due diligence and are realistic and commercial in their negotiations to avoid added time and costs of seeking to pass too much risk to the private sector.

For More Information Contact:

Tarmina Dent
TPP Law Limited
53 Great Suffolk Street
London SE1 ODB

t 020 7620 0888
f 020 7620 0778
e info@tpplaw.co.uk

Email:  Tarmina

For a full printable version of this
article please
click here

tttBACK

 Disclaimer  Privacy Statement

© 2010 TPP Law Limited

Friday, 10 September 2010